Study for the Idaho Real Estate Exam. Prepare with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When must a mechanic's lien be filed in Idaho by a carpet installer?

  1. 30 days from project completion

  2. 60 days from last work performed

  3. 90 days from project start

  4. 120 days from completing their work

The correct answer is: 120 days from completing their work

The correct answer centers around the timeline for filing a mechanic's lien in Idaho, which is crucial for those who have provided labor or materials for a construction project and wish to secure payment. In Idaho, a carpet installer has 120 days from the completion of their work to file a mechanic's lien. This period allows sufficient time for the installer to ensure that they have completed their work and to seek remedy if payment has not been made. The rationale behind the 120-day timeframe is to balance the interests of contractors and property owners, providing a clear window for lien filing while ensuring that contractors can protect their rights to payment. Understanding the context of other options helps clarify why they do not fit the requirements. For instance, 30 days and 60 days may seem like reasonable timeframes, but they do not align with Idaho's statutes regarding mechanic's liens, which establish a longer time to account for potential backlogs in payment processing or disputes that may arise post-completion. The 90-day option also does not meet the statutory requirements, as the law provides a more extended period for lien filing. Having this knowledge helps contractors and suppliers in managing their projects and payments effectively.